HGS6Pitt Posted May 8, 2015 Share Posted May 8, 2015 greetings everyone, Currently I am working on a simulation for my research and I am considering different staff schedules I would like to be able to have overlapping schedules for my workers and would like to be able to change the number of workers working in different time periods. for example, I would like to add 2 extra workers in busy period. is there a built in Simio feature that can help. Thank you very much Link to comment Share on other sites More sharing options...
dsturrock Posted June 14, 2015 Share Posted June 14, 2015 If you are creating a manual schedule you have full control and can change the capacity of any resource at any time. If you are using Simio schedules you can put a property in the value field and change that via the experiment window. I am not sure, but I believe that you can use a Simio schedule and also manually change the capacity value and that manual change will stay until the next automatic change. Link to comment Share on other sites More sharing options...