j.grant Posted October 7, 2019 Share Posted October 7, 2019 Hi All, I have a query. Is there a way to implement logic that allows the model to vary the processing time of a server as a function of the available man power? In my model I have various servers and all need a specific number of workers in order to begin processing. I have one large pool of workers to be shared between all stations. This means that there are times when all the workers are in use and times when some are spare. Ideally I would like to model that when there are men spare they would come and help other stations and get the job done quicker or when only some of the required quota of workers are seized they can start the work all be it at slower pace until the full quota has been seized. I hope this makes sense Thanks Link to comment Share on other sites More sharing options...
carlos Posted October 11, 2019 Share Posted October 11, 2019 I tried to do the same thing but with sequence task in a server Link to comment Share on other sites More sharing options...