ZanStern Posted April 28, 2022 Posted April 28, 2022 Hi I want to know if there is any possibility to have same schedule table, where you refer to different Table based WorkingSchedules? If you look in attached file you can see Example1, that represent what I need but I don't like this approach because there will be too many tables. Example3 on the other hand is something I want to achieve. Workers_MM.spfx
ZanStern Posted May 24, 2022 Author Posted May 24, 2022 If anyone will come to the same problem. In Example3 --> table Delavci --> column Delavec you just need to change the property Auto-set Table Row Reference to "True".