jfulton Posted January 24, 2023 Share Posted January 24, 2023 I have an instance in which I am using task sequences and I need to turn "auto cancel trigger" to none. There is a task that is dependent on whether or not the previous task actually occurred so I was going to add a conditional statement to the table. How can I go about writing an expression to check whether the previous task (also a predecessor) actually got executed or cancelled? Is there a nested expression I can take advantage of? Link to comment Share on other sites More sharing options...
ttarkan Posted February 9, 2023 Share Posted February 9, 2023 So lets say task B is dependent on Task A, hence Task A has sequence value 10 and Task B has sequence value 20 (Task A preceeds TaskB). Task A branch type should be conditional and for the condition formula should be written in to the "condition or probability" fieldç For Task B enter the processing time and other data as usual. If the auto-cancel trigger is set to "All immediate predecessors cancelled" (as it is by default), Task B will be cancelled if the condition for Task A didnt return true value. Hope this helps 1 Link to comment Share on other sites More sharing options...
Recommended Posts